Uttar Pradesh
Near Varanasi International Airport, Babatpur
,
Pindra (Sub-district)
,
Varanasi
Published :
Aug 2026
|
Updated :
Township development, agricultural land acquisition, and compensation disputes: The Kashi Dwar project in Varanasi
Reported by
Raj Shekhar
Legal Review by
Anmol Gupta
Rakshit Dhhingra, Amrita Chekkutty
Edited by
Anupa Kujur
2000
Households affected
15000
People affected
2024
Year started
387.29
ha.
Land area affected
2000
Households affected
15000
People Affected
2024
Year started
387.29
Land area affected
Key Insights
Sector
Infrastructure
Reason/Cause of conflict
Urban Development (Other than Smart Cities)
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Rural
Unclassifed
Sector
Infrastructure
Reason/Cause of conflict
Urban Development (Other than Smart Cities)
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Rural
Ended
1
Summary

The Kashi Dwar Project is a proposed large-scale township and infrastructure development by the Uttar Pradesh Housing and Development Board (UPHDB) in Varanasi. Located near Lal Bahadur Shastri International Airport in Babatpur, the proposed township would involve the acquisition of over 957 acres of land across 10 villages in Pindra tehsil: Pindra, Chakindar, Chanauli, Kaithauli, Samogra, Jaddupur, Raghunathpur, Roh, Pindrai and Belwa. The total project is estimated to cost around Rs 6,964.18 crore.

The project is intended to accommodate the city’s growing population through the development of a high-tech township. However, villagers who have lived in the area for generations have opposed the proposed land acquisition, citing the loss of their primary source of livelihood, inadequate compensation and the potential displacement of families from their villages.

According to villagers, around 15,000 people could be affected by the proposed acquisition, as agriculture and land-based activities are their primary sources of livelihood. Residents have been protesting against the project since 2023. Following sustained protests, Pindra MLA Dr Awadhesh Singh assured villagers that their land would not be acquired for the township and indicated that the project had been called off. However, villagers say that the sale and purchase of land in the 10 villages has remained restricted for nearly two years, creating uncertainty and affecting families’ livelihoods and daily lives.

A major point of contention is the compensation proposed for the land. According to the villagers, the government has proposed calculating compensation based on the official circle rate, which they claim is nearly half the prevailing market value of the land. They argue that such compensation would be inadequate given their dependence on the land for their livelihoods.

Villagers raised concerns over the compensation process under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. They contended that compensation should reflect the prevailing market value of the land rather than merely the government’s circle rate. They have also questioned the authorities’ handling of the acquisition process and the uncertainty surrounding the status of their land.

In February 2026, the Pindra MLA informed reporters that farmers whose land is covered by this scheme are being offered a fair compensation of four times the circle rate, an additional 24 percent increase over the base rate, and the entire process is being conducted entirely on a consensus basis.

The villagers have also pointed to previous land acquisitions in the area. Around 300 acres were reportedly acquired for a cultural centre, 350 acres for an airport expansion and 50 acres for a CRPF training centre. Residents argue that successive acquisitions have significantly reduced the amount of land available to sustain local families. Member of Parliament Priya Saroj has also raised the issue in Parliament.

Villagers told LCW researcher that the protests have reportedly faced police pressure, with community leaders allegedly threatened with arrest and criminal cases for opposing the proposed acquisition. Villagers and community representatives have also expressed concern over limited political support, which they say has weakened the movement.

2
Fact Sheet

Demand/Contention of the Affected Community

Demand to cancel the project

Refusal to give up land for the project

Other Demand/Contention of the Affected Community

Region Classification

Rural

Type of Land

Common and Private

Non-Forest (Grazing Land), Non-Forest (Other than Grazing Land)

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Details of sources (names of accused, names and numbers of any lawyers, names of any police officers contacted)

Status of Project

Original Project Deadline

Whether the Project has been Delayed

Significance of Land to Land Owners/Users

Agricultural land, Dwelling/habitation use, Grazing, Other natural resource collection/dependence, Ecosystem/Environmental Services, Water bodies

Whether the project was stalled due to land conflict

Source/Reference

Total investment involved (in Crores):

₹

6964

Type of investment:

Cost of Project

Year of Estimation

Page Number In Investment Document:

Has the Conflict Ended?

No

When did it end?

Why did the conflict end?

4
Additional Information

Government Departments Involved in the Conflict:

Uttar Pradesh Housing and Development Board, Varanasi

PSUs Involved in the Conflict:

Did LCW Approach Government Authorities for Comments?

No

Name, Designation and Comment of the Government Authorities Approached

Corporate Parties Involved in the Conflict:

Did LCW Approach Corporate Parties for Comments?

Communities/Local Organisations in the Conflict:

5
Information on the use of criminal law

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Legal Supporting Documents