The Madhya Pradesh state government, in December 2019, awarded a mining lease for the Bunder Diamond Block to Essel Mining & Industries Limited, an Aditya Birla Group company. The Bunder block is spread over 364 hectares of forest area in Sogoriya village in Buxwaha tehsil. The block is estimated to have 34 million carats of rough diamonds (diamonds occurring naturally inside the earth). The district administration has diverted 382 hectares of forestland for the project.
Two petitions filed in the National Green Tribunal (NGT) by P G Najpande and Ujjwal Sharma claimed that the project will cause deforestation by cutting four lakh trees and will exacerbate the water crisis in the Bundelkhand region. The petition also noted that the government cleared the project in violation of several environmental laws. Accepting the arguments put forward by the petitioner, the NGT bench imposed an interim stay on the project in July 2021. The bench also noted several legal anomalies, including violation of the Forest Conservation Act of 1980, failure to get permission for groundwater extraction, lack of a comprehensive environmental impact assessment, and the absence of a working plan for the conservation of wildlife.
Rambabu Tiwari, a local student activist working on water issues in Bundelkhand and part of the Save Buxwaha campaign, told LCW, “The company has succeeded in brainwashing the village people. They are supporting the project because the company has promised them employment, flats, roads, and airports at the cost of unsustainable development and indiscriminate exploitation of natural resources like forests and water.” Expressing concern about the fate of forests in Buxwaha, Tiwari added that the campaign was losing momentum as the company was more powerful and had more resources at its disposal. “They have the support of the government, but this project is harmful for the region,” he said.
Similar protests were witnessed earlier in 2016 when a mining lease was granted to the Australian mining company Rio Tinto. However, the company made an unexpected exit from the deal in 2017, which was later taken over by the state. Speculation suggested environmental concerns and resistance from the community were the reason for the exit. However, another report by ETV Bharat in 2025 suggested that the company left because of not being granted acreage they were demanding.
In a series of petitions filed before it, the Madhya Pradesh High Court, in its interim order dated 26 October 2021, directed the respondent company not to commence any mining or construction activities in Buxwaha without the its permission.
As per a report in November 2024, the leaseholder company Essel Mining surrendered the lease due to ongoing litigation and an interim stay by the High Court on mining activities in Buxwaha. However, it was reported that the state government is planning to auction the lease again, after presenting arguments before the High Court, praying for vacation of the interim order.
As of March 2026, the matter is still pending before the High Court, and no effective order has been passed by the court since January 2022.
Demand/Contention of the Affected Community
Opposition against environmental degradation
Demand to retain/protect access to common land/resources
Complaint against procedural violations
Other Demand/Contention of the Affected Community
Region Classification
Rural
Type of Land
Common
Forest
What was the action taken by the police?
How many people did the police detain or arrest?
What is the current status of the detained/accused persons?
Did the person face any violence while in police custody?
If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?
If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?
Legislation under which the accused was charged
Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?
In cases where the accused person approached the court for bail, was bail granted?
Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?
Details of sources (names of accused, names and numbers of any lawyers, names of any police officers contacted)
Status of Project
Project stalled
Original Project Deadline
2033
Whether the Project has been Delayed
No
Significance of Land to Land Owners/Users
Other environmental services
Whether the project was stalled due to land conflict
Yes
Source/Reference
<https://india.mongabay.com/2021/06/two-lakh-trees-and-water-security-at-stake-in-buxwahas-bunder-diamond-mining-project/>
Total investment involved (in Crores):
₹
2500
Type of investment:
Cost of Project
Year of Estimation
2019
Has the Conflict Ended?
No
When did it end?
Why did the conflict end?
Categories of Legislations Involved in the Conflict
Forest and Scheduled Area Governance Laws, Case Laws, Land Reform Laws, Forest and Scheduled Area Governance Laws, Central/State Government Policy, Other
Legislations/Policies Involved
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.
Whether claims/objections were made as per procedure in the relevant statute
What was the claim(s)/objection(s) raised by the community?
What was the Decision of the Concerned Government Department?
Legal Processes and Loopholes Enabling the Conflict:
Violation of environmental laws
Legal Status:
In Court
Status of Case In Court
Pending
Whether any adjudicatory body was approached
Yes
Name of the adjudicatory body
National Green Tribunal (Central Zone)
Name(s) of the Court(s)
High Court of Madhya Pradesh at Jabalpur
Case Number
O.A. 34/2021 and 35/2021 (CZ) ; WP/9742/2021
Main Reasoning/Decision of court
Major Human Rights Violations Related to the Conflict:
Whether criminal law was used against protestors:
No
Reported Details of the Violation:
Date of Violation
Location of Violation
Government Departments Involved in the Conflict:
Forest department, Ministry of Environment, Forests and Climate Change
PSUs Involved in the Conflict:
Did LCW Approach Government Authorities for Comments?
No
Name, Designation and Comment of the Government Authorities Approached
LCW reached out to Krishan Sinha, general manager, Essel Mining & Industries Limited, via phone and email but did not get any response.
Corporate Parties Involved in the Conflict:
Essel Mining & Industries Limited
Did LCW Approach Corporate Parties for Comments?
Yes
Communities/Local Organisations in the Conflict:
National Alliance of People's Movement, Save Buxwaha Movement
What was the action taken by the police?
How many people did the police detain or arrest?
What is the current status of the detained/accused persons?
Did the person face any violence while in police custody?
If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?
If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?
Legislation under which the accused was charged
Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?
In cases where the accused person approached the court for bail, was bail granted?
Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?
Were there any other notable irregularities that took place, or other significant details?