Tripura
Romola, Herma, Koroimura (Charilam), Mandabakilla village (Bishalgarh sub-division), Haldi Charra, Unakoti district
,
Bishalgarh
,
Sepahijala
Published :
Jul 2024
|
Updated :
In Tripura, villagers protest against ONGC exploration activities after blasts damage houses, pollute water bodies
Reported by
East Street Journal Asia
Legal Review by
Anmol Gupta
Edited by
Anupa Kujur
250
Households affected
1200
People affected
2023
Year started
ha.
Land area affected
250
Households affected
1200
People Affected
2023
Year started
Land area affected
Key Insights
Sector
Industry
Reason/Cause of conflict
Petroleum and Gas
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Rural
Ended
Sector
Industry
Reason/Cause of conflict
Petroleum and Gas
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Rural
Ended
1
Summary

Several villages in Tripura have been protesting against exploration activities carried out by Oil and Natural Gas Corporation Ltd (ONGC), alleging damages to houses and roads and demanding compensation.

On 23 January 2024, villagers of Haldi Charra, Unakoti, in the Tripura district, made a collective decision to halt all work related to construction project undertaken by ONGC as a sign of unity. The villagers expressed distress over the damage caused to their betel nut trees, ponds, local roads and houses due to the construction activities. Demanding fair compensation for the damages incurred, the villagers insisted that senior officials from ONGC engage in direct dialogue with them to address the issues at hand.

Similar protests erupted in Romola and Herma villages in the Charilam administrative block and Mandabakilla village under the Bishalgarh sub-division of the Sepahijala district against ONGC's gas exploration activities. They alleged that the drilling activities led to land degradation, water contamination, and disruption of agricultural activities, posing a threat to their well-being and way of life. Residents demanded compensation for damages to their houses due to dynamite blasts used by ONGC.

In April 2024, villagers of the West Charilam Koroimura area staged a protest against ONGC’s gas exploration and drilling project work. They said that around 250 houses in their village developed cracks due to ONGC's exploration activities and demanded compensation for the families affected by the project work.

The ONGC has been exploring gas in Tripura since 1962, discovering 11 gas fields and contributing to the ONGC Tripura Power Company Limited (OTPC) power plant in the Gomati district.

Tension escalated in May 2024 following clashes between the villagers of Mandabakilla and ONGC officials after the former trie to obstruct drilling activities. The ONGC filed a case against four individuals from the village at the Bishalgarh police station for allegedly impeding the drilling work.

Civil society organisations and human rights activists condemned the FIR filed against the villagers and labelled it as an attempt to suppress dissent.

2
Fact Sheet

Demand/Contention of the Affected Community

Demand for compensation

Opposition against environmental degradation

Demand to retain/protect access to common land/resources

Other Demand/Contention of the Affected Community

Region Classification

Rural

Type of Land

Common and Private

Non-Forest (Other than Grazing Land)

What was the action taken by the police?

Arrest

How many people did the police detain or arrest?

4

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

Don't Know

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

IPC, 1980

Section 188, Section 283

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Details of sources (names of accused, names and numbers of any lawyers, names of any police officers contacted)

Status of Project

Project underway despite protests

Original Project Deadline

Whether the Project has been Delayed

No

Significance of Land to Land Owners/Users

Agricultural land, Residential area, Water bodies, Other Natural Resource extraction/dependence

Whether the project was stalled due to land conflict

No

Source/Reference

Total investment involved (in Crores):

Type of investment:

Year of Estimation

Page Number In Investment Document:

Has the Conflict Ended?

No

When did it end?

Why did the conflict end?

4
Additional Information

Government Departments Involved in the Conflict:

Government of Tripura (GoT) , Sepahijala District Administration, Tripura Tribal Areas Autonomous District Council (TTADC)

PSUs Involved in the Conflict:

ONGC Tripura Power Company (OTPC), Oil & Natural Gas Corporation Ltd, GAIL India Limited

Did LCW Approach Government Authorities for Comments?

Name, Designation and Comment of the Government Authorities Approached

Corporate Parties Involved in the Conflict:

Did LCW Approach Corporate Parties for Comments?

Communities/Local Organisations in the Conflict:

5
Information on the use of criminal law

What was the action taken by the police?

Arrest

How many people did the police detain or arrest?

4

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

Don't Know

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

IPC, 1980

Section 188, Section 283

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Legal Supporting Documents

JOIN
THE LCW COMMUNITY
Exclusive monthly policy briefs, stories from the ground, Quarterly Analytics report, Curated Expert talks, merchandise and much more.


Support our work.
Sign Up Today
Author
Reported by
East Street Journal Asia

East Street Journal Asia is a multilingual, Web-based news journal. It is an independent media organisation whose goal is to make transparent, unbiased and data-driven journalism accessible to all.

Show more work
Latest updates
Surendranagar
Gujarat

Protests against solar power plant in Dhrangadhra’s Moti Malvan village in Gujarat

Tiruvannamalai
Tamil Nadu

Farmers protest new SIPCOT industrial complex project in Tamil Nadu's Thiruvannamalai

Visakhapatnam
Andhra Pradesh

Farmers demand compensation for land diverted for thermal power plant in Vishakhapatnam

Nainital
Uttarakhand

6 killed in Haldwani amid protest over demolition of mosque and madrasa

Pune
Maharashtra

Pune residents protest felling of trees for transit corridor, fear groundwater contamination

North Delhi
Delhi

DDA razes down encroachments near Azadpur Mandi in Delhi, 250 families rendered homeless

North West Delhi
Delhi

Residents of Delhi's Shakur Basti continue to live in fear of demolition

Jalgaon
Maharashtra

Farmers in Maharashtra's Jalgaon allege 1100 acres fraudulently acquired by solar power companies

Fact sheet

Demand/Contention of the Affected Community

Demand for compensation

Opposition against environmental degradation

Demand to retain/protect access to common land/resources

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Status of Project

Project underway despite protests

Original Project Deadline

Whether the Project has been Delayed

No

Significance of Land to Land Owners/Users

Agricultural land, Residential area, Water bodies, Other Natural Resource extraction/dependence

Whether the project was stalled due to land conflict

No

Source/Reference

JOIN
THE LCW COMMUNITY
Exclusive monthly policy briefs, stories from the ground, Quarterly Analytics report, Curated Expert talks, merchandise and much more.


Support our work.
Sign Up Today