Rajasthan
,
Nevta
,
Jaipur
Published :
Sep 2016
|
Updated :
Farmers Demand Higher Compensation, Return of Excess Land Acquired for Jaipur Ring Road Project (Southern Corridor)
Reported by
Manish Tiwari
Legal Review by
Anmol Gupta
Edited by
Anupa Kujur
Households affected
2400
People affected
2009
Year started
1692
ha.
Land area affected
Households affected
2400
People Affected
2009
Year started
1692
Land area affected
Key Insights
Sector
Infrastructure
Reason/Cause of conflict
Roads
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Urban
Ended
Sector
Infrastructure
Reason/Cause of conflict
Roads
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Urban
Ended
1
Summary

For over a decade, the construction of the 47 km long Jaipur Ring Road Southern Corridor by the Jaipur Development Authority (JDA) has remained pending, owing to problems related to land acquisition. While the JDA has maintained that it acquired 1,692 hectares of land from 500 families for the project connecting Ajmer Road, Tonk Road and Agra Road, farmers who are set to lose their lands held several protests demanding proper compensation and a change in design of the project among others. In 2011, the JDA selected Gurgaon based construction company Sanjose Supreme Joint Venture as the final bidder for the construction of the project. As there was little or no progress in the construction of the transport project, in 2017, the JDA signed a memorandum of Understanding (MoU) with the National Highways Authority of India (NHAI) to execute the project. The revised investment of the project was pegged at Rs 1,217 crore. For the project, landowners stated that the JDA acquired 360 metres from farmers to construct 90 metres of the transport corridor, and 135 metres on both sides of the road to construct a development corridor. Farmers led by Ring Road Sangarsh Samiti allege that the JDA is acquiring excess land in the name of the corridor. They demanded higher compensation and also return of excess land back to the cultivators. The land acquired also passes through forest area and an irrigation dam zone. The concerns raised by the forest department and irrigation department officials were settled by the JDA. In November 2020, some part of the ring road was made operational and presently the NHAI is constructing coverfield structures as part of the project. Reportedly, hundreds of affected farmers families are still awaiting promised compensation.

2
Fact Sheet

Demand/Contention of the Affected Community

Demand for more compensation than promised

Demand for promised compensation

Demand to get back acquired land

Complaint against procedural violations

Other Demand/Contention of the Affected Community

Region Classification

Urban

Type of Land

Both

Forest and Non-Forest

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Details of sources (names of accused, names and numbers of any lawyers, names of any police officers contacted)

Status of Project

Original Project Deadline

Whether the Project has been Delayed

Significance of Land to Land Owners/Users

Whether the project was stalled due to land conflict

Source/Reference

Total investment involved (in Crores):

1216.67

Type of investment:

Revised Investment

Year of Estimation

Page Number In Investment Document:

Has the Conflict Ended?

No

When did it end?

Why did the conflict end?

4
Additional Information

Government Departments Involved in the Conflict:

Jaipur Development Authority, National Highways Authority of India

PSUs Involved in the Conflict:

Did LCW Approach Government Authorities for Comments?

No

Name, Designation and Comment of the Government Authorities Approached

Corporate Parties Involved in the Conflict:

Did LCW Approach Corporate Parties for Comments?

Communities/Local Organisations in the Conflict:

Ring Road Sangarsh Samiti

5
Information on the use of criminal law

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Legal Supporting Documents

JOIN
THE LCW COMMUNITY
Exclusive monthly policy briefs, stories from the ground, Quarterly Analytics report, Curated Expert talks, merchandise and much more.


Support our work.
Sign Up Today
Author
Reported by
Manish Tiwari
Show more work
Latest updates
Ahmedabad
Gujarat

Ahmedabad civic body demolishes 292 illegal structures in Makarba, residents demand rehabilitation

Kachchh
Gujarat

Locals oppose GHCL's chemical plant project in Gujarat's Bada village

Karbi Anglong
Assam

Tribals demand cancellation of multiple corporate projects in Karbi Anglong

Morigaon
Assam

Assam villagers fight to save Hatiutha Hill from granite mining

Surat
Gujarat

Dispute erupts after officials demolish alleged encroachment by Jumma Masjid Trust in Surat

East Siang
Arunachal Pradesh

Locals demand relocation of silicon factory in East Siang citing pollution concerns

Nalbari
Assam

Nalbari locals raise environmental concerns over brick kiln, stone crusher operations in Pagladiya river

East Godavari
Andhra Pradesh

Polavaram irrigation project affected families in Andhra Pradesh still awaiting rehabilitation

Fact sheet

Demand/Contention of the Affected Community

Demand for more compensation than promised

Demand for promised compensation

Demand to get back acquired land

Complaint against procedural violations

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Status of Project

Original Project Deadline

Whether the Project has been Delayed

Significance of Land to Land Owners/Users

Whether the project was stalled due to land conflict

Source/Reference

JOIN
THE LCW COMMUNITY
Exclusive monthly policy briefs, stories from the ground, Quarterly Analytics report, Curated Expert talks, merchandise and much more.


Support our work.
Sign Up Today
Conflicts Map
Conflict Database
About Us